City of Colfax's Clay Street

2-E-986(001)-1

2-E-986(001)-1
Clay Street

Harrison to NE End

FY 2008 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $79,444

County: Whitman   |   Legislative District: 9   |   Project Length: 2,200.00   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 10/26/2007

Project Information

Lead Agency COLFAX
Funding Year 2008
Program SCPP
Current Phase Audit
Legislative District 9
Congressional District 5
Federal Route Number 9999
Project Length 2200.00 mi.
ADT 500
Functional Class Collector
Type of Work Resurfacing
Project Contact Andy Rogers
Contact Email arogers@ci.colfax.wa.us
TIB Engineer Jonathan Heusman
Last Payment Date 10/26/2007

Project Schedule

  Target Date Actual Date
Project Selection Date   07/03/2007
Delayed Project Date 07/01/2010  
Predesign Approval
Design Approval
Bid Auth. Approval 07/03/2007 07/03/2007
Construction Approval 07/15/2007 07/15/2007
Project Closeout 10/31/2007 10/26/2007
Audit Date   10/26/2007
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 98,000 79,444
Other Construction 0 0
Total Construction 98,000 79,444
     
Funding Surplus - 18,556  
Total TIB Funding 79,444 79,444

Local Funding Partners

Funding Amount Percent
COLFAX 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

The project provides a 2-in overlay of the roadway surface and repairs sidewalk, curb and gutter. The scope includes constructing ADA ramps at three locations.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments