The pavement condition rating for the segments were as follow Merclyn Lane 52 McCraken Avenue 32 Reed Street 46 D'Anjou Street 50
Projects — TIB Project Information
TIB Project Information
City of Zillah's FY 2022 Overlay Project
2-E-947(003)-1
2-E-947(003)-1
FY 2022 Overlay Project
Multiple Locations
FY 2022 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $186,950
County: Yakima | Legislative District: 15 | Project Length: 0.44 | TIB Engineer: Jonathan Heusman | Last Payment Date: 08/02/2021
Project Information
Lead Agency | ZILLAH |
Funding Year | 2022 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 15 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.44 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | John Simmons |
Contact Email | jsimmons@cityofzillah.us |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 08/02/2021 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/20/2020 | |
Delayed Project Date | 07/01/2023 | |
Predesign Approval | ||
Design Approval | 02/01/2021 | 12/08/2020 |
Bid Auth. Approval | 02/28/2021 | 02/24/2021 |
Construction Approval | 03/30/2021 | 03/31/2021 |
Project Closeout | 07/15/2021 | 07/19/2021 |
Audit Date | 08/02/2021 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 28,620 | 31,800 |
Right of Way | 0 | 0 |
Total Design | 28,620 | 31,800 |
Construction Engineering | 28,593 | 29,883 |
Construction Contract | 190,669 | 194,521 |
Other Construction | 0 | 1,137 |
Total Construction | 219,262 | 225,541 |
Funding Surplus | - 60,932 | |
Total TIB Funding | 186,950 | 257,341 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
ZILLAH | 70,391 | 27.4% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 70,391 | 27.4% |
Project Description
Grind existing asphalt by 2 inches, reuse as base. Resurface with 2 inch overlay
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |