Projects — TIB Project Information
TIB Project Information
City of Zillah's FY 2017 Overlay Project
2-E-947(001)-1
2-E-947(001)-1
FY 2017 Overlay Project
Multiple Locations
FY 2017 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $123,871
County: Yakima | Legislative District: 15 | Project Length: 0.26 | TIB Engineer: Jonathan Heusman | Last Payment Date: 11/29/2016
Project Information
Lead Agency | ZILLAH |
Funding Year | 2017 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 15 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.26 mi. |
ADT | 200 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Tim Tilley |
Contact Email | asteele@cityofzillah.us |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 11/29/2016 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/20/2015 | |
Delayed Project Date | 07/01/2018 | |
Predesign Approval | ||
Design Approval | 01/15/2016 | 12/29/2015 |
Bid Auth. Approval | 04/01/2016 | 03/28/2016 |
Construction Approval | 04/30/2016 | 04/12/2016 |
Project Closeout | 07/01/2016 | 11/14/2016 |
Audit Date | 11/29/2016 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 10,825 | 14,420 |
Right of Way | 0 | 0 |
Total Design | 10,825 | 14,420 |
Construction Engineering | 13,534 | 17,083 |
Construction Contract | 90,229 | 106,131 |
Other Construction | 0 | 0 |
Total Construction | 103,763 | 123,214 |
Funding Increase | 16,739 | |
Funding Surplus | - 7,456 | |
Total TIB Funding | 123,871 | 137,634 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
ZILLAH | 13,763 | 10.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 13,763 | 10.0% |
Project Description
This project will grind and overlay Glen Drive, Bartlett Avenue and 4th Street from First Ave. to Second Ave.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |