Projects — TIB Project Information
TIB Project Information
City of Tieton's 2024 Overlay
2-E-945(002)-1
2-E-945(002)-1
2024 Overlay
Naches Ave to Tieton Ave
FY 2025 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $95,150
County: Yakima | Legislative District: 13 | Project Length: 0.10 | TIB Engineer: Jonathan Heusman | Last Payment Date: 08/01/2024
Project Information
Lead Agency | TIETON |
Funding Year | 2025 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 13 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.10 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Frank Brewer |
Contact Email | fbtieton@gmail.com |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 08/01/2024 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/01/2023 | |
Delayed Project Date | 07/01/2026 | |
Predesign Approval | ||
Design Approval | 01/01/2024 | 12/07/2023 |
Bid Auth. Approval | 05/01/2024 | 04/05/2024 |
Construction Approval | 05/31/2024 | 04/24/2024 |
Project Closeout | 09/04/2024 | 07/17/2024 |
Audit Date | 08/01/2024 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 13,100 | 13,790 |
Right of Way | 0 | 0 |
Total Design | 13,100 | 13,790 |
Construction Engineering | 14,107 | 9,192 |
Construction Contract | 100,783 | 77,179 |
Other Construction | 0 | 0 |
Total Construction | 114,890 | 86,371 |
Funding Surplus | - 32,840 | |
Total TIB Funding | 95,150 | 100,161 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
TIETON | 5,011 | 5.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 5,011 | 5.0% |
Project Description
2' overlay of travel lanes. Replace pavement markings. No increase project was advertised without TIB approval
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |