Town of Naches's FY 2020 Overlay Project

2-E-944(003)-1

2-E-944(003)-1
FY 2020 Overlay Project

Multiple Locations

FY 2020 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $155,286

County: Yakima   |   Legislative District: 14   |   Project Length: 0.24   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 01/02/2020

Project Information

Lead Agency NACHES
Funding Year 2020
Program SCPP
Current Phase Audit
Legislative District 14
Congressional District 4
Federal Route Number 4876
Project Length 0.24 mi.
ADT 0
Functional Class Collector
Type of Work Resurfacing
Project Contact Jeff Ranger
Contact Email Jeff.Ranger@co.yakima.wa.us
TIB Engineer Jonathan Heusman
Last Payment Date 01/02/2020

Project Schedule

  Target Date Actual Date
Project Selection Date   11/16/2018
Delayed Project Date 07/01/2021  
Predesign Approval
Design Approval 01/01/2019 12/04/2018
Bid Auth. Approval 04/01/2019 03/08/2019
Construction Approval 04/30/2019 05/01/2019
Project Closeout 12/31/2019 12/09/2019
Audit Date   01/02/2020
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 16,120 16,120
Right of Way 0 0
Total Design 16,120 16,120
     
Construction Engineering 20,150 20,150
Construction Contract 134,300 115,215
Other Construction 0 4,236
Total Construction 154,450 139,601
     
Funding Increase 7,272  
Funding Surplus - 22,556  
Total TIB Funding 155,286 155,721

Local Funding Partners

Funding Amount Percent
NACHES 435 0.3%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 435 0.3%

Project Description

Grinding and overlaying (0.17') Shafer Avenue from US Highway 12 to Marvin Street. This route is heavily traveled as it provides a direct link between State Route 12 and Old Naches Highway. In anticipation of this resurfacing project, the Town has replaced all mainline water valves and will be replacing water service lines to avoid open cut trenching following project completion.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.