Town of Naches's FY 2018 Seal Coat Project
2-E-944(001)-1
2-E-944(001)-1
FY 2018 Seal Coat Project
Multiple Locations
FY 2018 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $41,000
County: Yakima | Legislative District: 14 | Project Length: 0.25 | TIB Engineer: Jonathan Heusman | Last Payment Date: 12/27/2017
Project Information
Lead Agency | NACHES |
Funding Year | 2018 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 14 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.25 mi. |
ADT | 250 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Jeff Ranger |
Contact Email | jeff.ranger@co.yakima.wa.us |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 12/27/2017 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/18/2016 | |
Delayed Project Date | 07/01/2019 | |
Predesign Approval | ||
Design Approval | 01/01/2017 | 01/10/2017 |
Bid Auth. Approval | 04/01/2017 | 01/10/2017 |
Construction Approval | 05/01/2017 | 06/21/2017 |
Project Closeout | 01/31/2018 | 12/27/2017 |
Audit Date | 12/27/2017 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 1,774 |
Right of Way | 0 | 0 |
Total Design | 0 | 1,774 |
Construction Engineering | 0 | 0 |
Construction Contract | 30,597 | 40,092 |
Other Construction | 0 | 0 |
Total Construction | 30,597 | 40,092 |
Funding Increase | 10,403 | |
Total TIB Funding | 41,000 | 41,866 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
NACHES | 866 | 2.1% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 866 | 0.0% |
Project Description
This project will crack seal, repair areas of pavement failure and chip seal the following segments Moxee Avenue - 2nd St to 4th St Sinclair Avenue - Marvin St to 3rd St
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |