The pavement condition rating of Beaudry Road - 90ft s/o Postma Rd to 1030ft n/o Postma Rd 63
Projects — TIB Project Information
TIB Project Information
City of Moxee's FY 2021 Seal Coat Project
2-E-943(005)-1
2-E-943(005)-1
FY 2021 Seal Coat Project
Multiple Locations
FY 2021 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $13,222
County: Yakima | Legislative District: 15 | Project Length: 0.22 | TIB Engineer: Jonathan Heusman | Last Payment Date: 02/16/2021
Project Information
Lead Agency | MOXEE |
Funding Year | 2021 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 15 |
Congressional District | 4 |
Federal Route Number | 4645 |
Project Length | 0.22 mi. |
ADT | 0 |
Functional Class | Minor |
Type of Work | Resurfacing |
Project Contact | Byron Adams |
Contact Email | byron.adams@co.yakima.wa.us |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 02/16/2021 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2019 | |
Delayed Project Date | 07/01/2022 | |
Predesign Approval | ||
Design Approval | 02/01/2020 | 12/24/2019 |
Bid Auth. Approval | 05/01/2020 | 12/24/2019 |
Construction Approval | 05/31/2020 | 12/24/2019 |
Project Closeout | 01/31/2021 | 02/04/2021 |
Audit Date | 02/16/2021 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 19,000 | 13,918 |
Other Construction | 0 | 0 |
Total Construction | 19,000 | 13,918 |
Funding Surplus | - 5,778 | |
Total TIB Funding | 13,222 | 13,918 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
MOXEE | 696 | 5.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 696 | 5.0% |
Project Description
The City will chip seal Beaudry Road 90 ft s/o Postma Rd to 1,030 ft n/o Postma Rd and restripe. The City will use Yakima county services for all work.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |