City of Moxee's FY 2009 Sidewalk Maintenance Project

2-E-943(002)-1

2-E-943(002)-1
FY 2009 Sidewalk Maintenance Project

Multiple Locations

FY 2009 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $7,712

County: Yakima   |   Legislative District: 15   |   Project Length: 144.00   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 03/17/2010

Project Information

Lead Agency MOXEE
Funding Year 2009
Program SCPP
Current Phase Audit
Legislative District 15
Congressional District 4
Federal Route Number 9999
Project Length 144.00 mi.
ADT 250
Functional Class Local Access
Type of Work Pedestrian
Project Contact Byron Adams
Contact Email byronadams@charter.net
TIB Engineer Jonathan Heusman
Last Payment Date 03/17/2010

Project Schedule

  Target Date Actual Date
Project Selection Date   11/16/2007
Delayed Project Date 07/01/2010  
Predesign Approval
Design Approval 01/01/2008 09/09/2008
Bid Auth. Approval 01/01/2008 09/09/2008
Construction Approval 02/25/2010 02/25/2010
Project Closeout 04/30/2010 03/17/2010
Audit Date   03/17/2010
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 7,712 8,102
Other Construction 0 0
Total Construction 7,712 8,102
     
Total TIB Funding 7,712 8,102

Local Funding Partners

Funding Amount Percent
MOXEE 390 4.8%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 390 4.8%

Project Description

This project will repair 144 feet of existing sidewalk and install ADA ramps as needed along the west side of South Holly Drive between Moxee Avenue and Holly Place.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.