TIB Project Information

City of Mabton's 2024 Otta Seal

2-E-942(006)-1

2-E-942(006)-1
2024 Otta Seal

Multiple Locations

FY 2024 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $562,968

County: Yakima   |   Legislative District: 15   |   Project Length: 5.00   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 03/17/2025

Project Information

Lead Agency MABTON
Funding Year 2024
Program SCPP
Current Phase Audit
Legislative District 15
Congressional District 4
Federal Route Number 9999
Project Length 5.00 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Syylvia Sanchez
Contact Email sylvia.sanchez@co.yakima.wa.us
TIB Engineer Jonathan Heusman
Last Payment Date 03/17/2025

Project Schedule

  Target Date Actual Date
Project Selection Date   12/12/2022
Delayed Project Date 07/01/2025  
Predesign Approval
Design Approval 01/20/2023 02/24/2023
Bid Auth. Approval 05/01/2024 05/08/2024
Construction Approval 05/15/2024 05/31/2024
Project Closeout 12/31/2024 03/10/2025
Audit Date   03/17/2025
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 15,000 15,000
Right of Way 0 0
Total Design 15,000 15,000
     
Construction Engineering 65,000 62,456
Construction Contract 576,777 485,512
Other Construction 0 0
Total Construction 641,777 547,968
     
Funding Surplus - 93,809  
Total TIB Funding 562,968 562,968

Local Funding Partners

Funding Amount Percent
MABTON 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

Otta Seal the low volume residential streets in the City.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments