City of Mabton's FY 2017 Overlay Project

2-E-942(003)-1

2-E-942(003)-1
FY 2017 Overlay Project

Multiple Locations

FY 2017 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $315,208

County: Yakima   |   Legislative District: 15   |   Project Length: 0.53   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 01/16/2018

Project Information

Lead Agency MABTON
Funding Year 2017
Program SCPP
Current Phase Audit
Legislative District 15
Congressional District 4
Federal Route Number 9999
Project Length 0.53 mi.
ADT 200
Functional Class TIB Arterial
Type of Work Reconstruction
Project Contact Mario Martinez
Contact Email mario.martinez@co.yakima.wa.us
TIB Engineer Jonathan Heusman
Last Payment Date 01/16/2018

Project Schedule

  Target Date Actual Date
Project Selection Date   11/20/2015
Delayed Project Date 07/01/2018  
Predesign Approval
Design Approval 01/15/2016 12/14/2015
Bid Auth. Approval 06/01/2016 06/20/2016
Construction Approval 07/20/2016 07/27/2016
Project Closeout 12/31/2017 12/28/2017
Audit Date   01/16/2018
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 45,900 40,250
Right of Way 0 0
Total Design 45,900 40,250
     
Construction Engineering 23,760 26,400
Construction Contract 239,940 289,776
Other Construction 0 0
Total Construction 263,700 316,176
     
Funding Increase 19,370  
Funding Surplus - 13,762  
Total TIB Funding 315,208 356,426

Local Funding Partners

Funding Amount Percent
MABTON 41,218 11.5%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 41,218 11.1%

Project Description

This project uses full depth reclaimation to restore the base and provides a 2-inch asphalt wearing course to the following segments South Street - Boundary Road to Main Street Boundary Road - SR 22 to Pine Street

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments