7th Avenue is in poor condition, the roadway surface has high percentage alligator cracking and evidence of base failure. These conditions result in the roadway needing to be reconstructed.
Projects — TIB Project Information
TIB Project Information
City of Mabton's 7th Avenue
2-E-942(002)-1
2-E-942(002)-1
7th Avenue
Adams Street to Monroe St
FY 2012 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $43,434
County: Yakima | Legislative District: 15 | Project Length: 0.09 | TIB Engineer: Jonathan Heusman | Last Payment Date: 06/03/2013
Project Information
Lead Agency | MABTON |
Funding Year | 2012 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 15 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.09 mi. |
ADT | 0 |
Functional Class | Local Access |
Type of Work | Reconstruction |
Project Contact | Angel Reyna |
Contact Email | aztec22@hotmail.com |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 06/03/2013 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 08/03/2011 | |
Delayed Project Date | 07/01/2014 | |
Predesign Approval | ||
Design Approval | 08/03/2011 | 08/03/2011 |
Bid Auth. Approval | 08/03/2011 | 08/03/2011 |
Construction Approval | 04/01/2012 | 03/13/2012 |
Project Closeout | 06/01/2013 | 05/14/2013 |
Audit Date | 06/03/2013 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 4,650 | 4,650 |
Right of Way | 0 | 0 |
Total Design | 4,650 | 4,650 |
Construction Engineering | 4,650 | 4,576 |
Construction Contract | 37,300 | 34,208 |
Other Construction | 0 | 0 |
Total Construction | 41,950 | 38,784 |
Funding Surplus | - 3,166 | |
Total TIB Funding | 43,434 | 43,434 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
MABTON | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
This project will reconstruct 7th Avenue using base stabilization and a 2-inch overlay.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |