Projects — TIB Project Information
TIB Project Information
City of Mabton's FY 2009 Overlay Project
2-E-942(001)-1
2-E-942(001)-1
FY 2009 Overlay Project
Multiple Locations
FY 2009 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $91,968
County: Yakima | Legislative District: 15 | Project Length: 0.51 | TIB Engineer: Jonathan Heusman | Last Payment Date: 12/10/2008
Project Information
Lead Agency | MABTON |
Funding Year | 2009 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 15 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.51 mi. |
ADT | 250 |
Functional Class | Local Access |
Type of Work | Resurfacing |
Project Contact | Alan Rainey |
Contact Email | alan.spinkengineering@verizon.net |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 12/10/2008 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/16/2007 | |
Delayed Project Date | 07/01/2010 | |
Predesign Approval | ||
Design Approval | 01/01/2008 | 03/05/2008 |
Bid Auth. Approval | 01/01/2008 | 09/23/2008 |
Construction Approval | 09/01/2008 | 09/29/2008 |
Project Closeout | 10/31/2008 | 12/04/2008 |
Audit Date | 12/10/2008 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 4,536 | 22,580 |
Right of Way | 0 | 0 |
Total Design | 4,536 | 22,580 |
Construction Engineering | 2,404 | 8,976 |
Construction Contract | 45,190 | 165,066 |
Other Construction | 0 | 0 |
Total Construction | 47,594 | 174,042 |
Funding Increase | 39,838 | |
Total TIB Funding | 91,968 | 196,622 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
MABTON | 104,654 | 53.2% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 104,654 | 53.2% |
Project Description
This project consists of a 2 inch overlay and base stabilization of the following segments 3rd Avenue - Monroe Street to Washington Street 4th Avenue - Monroe Street to Washington Street 5th Avenue - Monroe Street to Washington Street
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |