TIB Project Information

City of Mabton's FY 2009 Overlay Project

2-E-942(001)-1

2-E-942(001)-1
FY 2009 Overlay Project

Multiple Locations

FY 2009 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $91,968

County: Yakima   |   Legislative District: 15   |   Project Length: 0.51   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 12/10/2008

Project Information

Lead Agency MABTON
Funding Year 2009
Program SCPP
Current Phase Audit
Legislative District 15
Congressional District 4
Federal Route Number 9999
Project Length 0.51 mi.
ADT 250
Functional Class Local Access
Type of Work Resurfacing
Project Contact Alan Rainey
Contact Email alan.spinkengineering@verizon.net
TIB Engineer Jonathan Heusman
Last Payment Date 12/10/2008

Project Schedule

  Target Date Actual Date
Project Selection Date   11/16/2007
Delayed Project Date 07/01/2010  
Predesign Approval
Design Approval 01/01/2008 03/05/2008
Bid Auth. Approval 01/01/2008 09/23/2008
Construction Approval 09/01/2008 09/29/2008
Project Closeout 10/31/2008 12/04/2008
Audit Date   12/10/2008
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 4,536 22,580
Right of Way 0 0
Total Design 4,536 22,580
     
Construction Engineering 2,404 8,976
Construction Contract 45,190 165,066
Other Construction 0 0
Total Construction 47,594 174,042
     
Funding Increase 39,838  
Total TIB Funding 91,968 196,622

Local Funding Partners

Funding Amount Percent
MABTON 104,654 53.2%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 104,654 53.2%

Project Description

This project consists of a 2 inch overlay and base stabilization of the following segments 3rd Avenue - Monroe Street to Washington Street 4th Avenue - Monroe Street to Washington Street 5th Avenue - Monroe Street to Washington Street

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.