Town of Prescott's FY 2020 Seal Coat Project

2-E-937(001)-1

2-E-937(001)-1
FY 2020 Seal Coat Project

Multiple Locations

FY 2020 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $61,019

County: Walla Walla   |   Legislative District: 16   |   Project Length: 1.31   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 09/03/2019

Project Information

Lead Agency PRESCOTT
Funding Year 2020
Program SCPP
Current Phase Audit
Legislative District 16
Congressional District 5
Federal Route Number 9999
Project Length 1.31 mi.
ADT 0
Functional Class Local Access
Type of Work Resurfacing
Project Contact Steve Heimbigner
Contact Email steve.h42@hotmail.com
TIB Engineer Jonathan Heusman
Last Payment Date 09/03/2019

Project Schedule

  Target Date Actual Date
Project Selection Date   04/01/2019
Delayed Project Date 07/01/2021  
Predesign Approval 04/01/2019
Design Approval 04/30/2019 04/17/2019
Bid Auth. Approval 04/30/2019 04/17/2019
Construction Approval 04/30/2019 04/17/2019
Project Closeout 12/31/2019 08/15/2019
Audit Date   09/03/2019
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 61,019 69,166
Other Construction 0 0
Total Construction 61,019 69,166
     
Total TIB Funding 61,019 69,166

Local Funding Partners

Funding Amount Percent
PRESCOTT 0 0.0%
WSDOT Funding 0 0.0%
Port of Walla Walla  8,147 11.8%
 
 
 
 
 
 
 
Total Local Funding 8,147 0.0%

Project Description

This project will chip seal multiple roads throughout Prescott. There will be some pavement repair in various locations.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments