City of White Salmon's 2022 Seal Coat Award
2-E-936(006)-1
2-E-936(006)-1
2022 Seal Coat Award
Multiple Locations
FY 2024 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $161,064
County: Klickitat | Legislative District: 14 | Project Length: 1.57 | TIB Engineer: Chris Langhoff | Last Payment Date: 04/15/2024
Project Information
Lead Agency | WHITE SALMON |
Funding Year | 2024 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 14 |
Congressional District | 3 |
Federal Route Number | 9999 |
Project Length | 1.57 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Jan Brending |
Contact Email | janb@ci.white-salmon.wa.us |
TIB Engineer | Chris Langhoff |
Last Payment Date | 04/15/2024 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/02/2022 | |
Delayed Project Date | 07/01/2025 | |
Predesign Approval | ||
Design Approval | 02/01/2023 | 01/25/2023 |
Bid Auth. Approval | 06/15/2023 | 01/25/2023 |
Construction Approval | 02/15/2024 | 01/31/2024 |
Project Closeout | 02/29/2024 | 04/05/2024 |
Audit Date | 04/15/2024 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 7,113 | 0 |
Right of Way | 0 | 0 |
Total Design | 7,113 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 277,387 | 169,818 |
Other Construction | 0 | 0 |
Total Construction | 277,387 | 169,818 |
Funding Surplus | - 123,436 | |
Total TIB Funding | 161,064 | 169,818 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
WHITE SALMON | 8,754 | 5.2% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 8,754 | 5.2% |
Project Description
Chip seal and crack seal with county crews
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |