TIB Project Information

Town of South Cle Elum's FY 2022 Seal Coat Project

2-E-933(003)-1

2-E-933(003)-1
FY 2022 Seal Coat Project

Multiple Locations

FY 2022 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $30,893

County: Kittitas   |   Legislative District: 13   |   Project Length: 0.77   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 11/30/2021

Project Information

Lead Agency SOUTH CLE ELUM
Funding Year 2022
Program SCPP
Current Phase Audit
Legislative District 13
Congressional District 8
Federal Route Number 9999
Project Length 0.77 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Scott MacKenzie
Contact Email southce@gmail.com
TIB Engineer Jonathan Heusman
Last Payment Date 11/30/2021

Project Schedule

  Target Date Actual Date
Project Selection Date   11/20/2020
Delayed Project Date 07/01/2023  
Predesign Approval
Design Approval 02/01/2021 12/27/2020
Bid Auth. Approval 04/01/2021 03/23/2021
Construction Approval 03/24/2021 03/25/2021
Project Closeout 10/31/2021 11/18/2021
Audit Date   11/30/2021
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 1,304 125
Construction Contract 26,084 40,436
Other Construction 0 0
Total Construction 27,388 40,561
     
Funding Increase 3,505  
Total TIB Funding 30,893 40,561

Local Funding Partners

Funding Amount Percent
SOUTH CLE ELUM 9,668 23.8%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 9,668 0.0%

Project Description

Chip and sweep

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments