Town of South Cle Elum's FY 2017 Seal Coat Project
2-E-933(001)-1
2-E-933(001)-1
FY 2017 Seal Coat Project
Multiple Locations
FY 2017 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $21,809
County: Kittitas | Legislative District: 13 | Project Length: 0.49 | TIB Engineer: Jonathan Heusman | Last Payment Date: 10/03/2016
Project Information
Lead Agency | SOUTH CLE ELUM |
Funding Year | 2017 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 13 |
Congressional District | 8 |
Federal Route Number | 9999 |
Project Length | 0.49 mi. |
ADT | 150 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Scott MacKenzie |
Contact Email | southce@gmail.com |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 10/03/2016 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/20/2015 | |
Delayed Project Date | 07/01/2018 | |
Predesign Approval | ||
Design Approval | 01/15/2016 | 12/02/2015 |
Bid Auth. Approval | 06/01/2016 | 12/02/2015 |
Construction Approval | 07/01/2016 | 12/02/2015 |
Project Closeout | 12/31/2016 | 09/22/2016 |
Audit Date | 10/03/2016 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 3,000 | 0 |
Right of Way | 0 | 0 |
Total Design | 3,000 | 0 |
Construction Engineering | 3,000 | 557 |
Construction Contract | 31,750 | 21,252 |
Other Construction | 0 | 0 |
Total Construction | 34,750 | 21,809 |
Funding Surplus | - 15,941 | |
Total TIB Funding | 21,809 | 21,809 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
SOUTH CLE ELUM | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
This project repairs areas of pavement failure, seals cracks and provides a chip seal of Lincoln Avenue between the West Town Limits and South Cle Elum Way.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |