City of Kittitas's FY 2018 Overlay Project

2-E-931(009)-1

2-E-931(009)-1
FY 2018 Overlay Project

Multiple Locations

FY 2018 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $76,070

County: Kittitas   |   Legislative District: 13   |   Project Length: 0.19   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 11/01/2017

Project Information

Lead Agency KITTITAS
Funding Year 2018
Program SCPP
Current Phase Audit
Legislative District 13
Congressional District 8
Federal Route Number 9999
Project Length 0.19 mi.
ADT 100
Functional Class Local Access
Type of Work Reconstruction
Project Contact Scott Moore
Contact Email scott.moore@cityofkittitas.com
TIB Engineer Jonathan Heusman
Last Payment Date 11/01/2017

Project Schedule

  Target Date Actual Date
Project Selection Date   11/18/2016
Delayed Project Date 07/01/2019  
Predesign Approval
Design Approval 01/01/2017 12/20/2016
Bid Auth. Approval 04/01/2017 12/20/2016
Construction Approval 05/01/2017 12/20/2016
Project Closeout 10/31/2017 10/17/2017
Audit Date   11/01/2017
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 10,400 16,264
Right of Way 0 0
Total Design 10,400 16,264
     
Construction Engineering 10,400 0
Construction Contract 74,200 59,806
Other Construction 0 0
Total Construction 84,600 59,806
     
Funding Surplus - 18,930  
Total TIB Funding 76,070 76,070

Local Funding Partners

Funding Amount Percent
KITTITAS 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

This project reconstructs 1000 feet of gravel streets, Spokane Street\1st Avenue\Okanogan Street, to a 24 foot paved roadway.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.