Projects — TIB Project Information
TIB Project Information
City of Kittitas's FY 2014 Overlay Project
2-E-931(005)-1
2-E-931(005)-1
FY 2014 Overlay Project
Multiple Locations
FY 2014 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $60,638
County: Kittitas | Legislative District: 13 | Project Length: 0.23 | TIB Engineer: Jonathan Heusman | Last Payment Date: 08/01/2013
Project Information
Lead Agency | KITTITAS |
Funding Year | 2014 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 13 |
Congressional District | 8 |
Federal Route Number | 9999 |
Project Length | 0.23 mi. |
ADT | 0 |
Functional Class | Local Access |
Type of Work | Reconstruction |
Project Contact | Tony Helland |
Contact Email | clerk@cityofkittitas.com |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 08/01/2013 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/16/2012 | |
Delayed Project Date | 07/01/2015 | |
Predesign Approval | ||
Design Approval | 01/01/2013 | 12/19/2012 |
Bid Auth. Approval | 06/01/2013 | 05/01/2013 |
Construction Approval | 06/02/2013 | 05/28/2013 |
Project Closeout | 07/15/2013 | 07/03/2013 |
Audit Date | 08/01/2013 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 7,207 | 16,693 |
Right of Way | 0 | 0 |
Total Design | 7,207 | 16,693 |
Construction Engineering | 2,402 | 0 |
Construction Contract | 50,450 | 43,945 |
Other Construction | 0 | 0 |
Total Construction | 52,852 | 43,945 |
Funding Increase | 579 | |
Total TIB Funding | 60,638 | 60,638 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
KITTITAS | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
The project will improve King Street from Patrick Ave to Railroad Ave. The existing roadway is gravel. It will be improved the base material and then overlayed with HMA.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |