TIB Project Information

City of Kittitas's FY 2009 Overlay Project

2-E-931(002)-1

2-E-931(002)-1
FY 2009 Overlay Project

Multiple Locations

FY 2009 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $116,736

County: Kittitas   |   Legislative District: 13   |   Project Length: 0.52   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 06/12/2008

Project Information

Lead Agency KITTITAS
Funding Year 2009
Program SCPP
Current Phase Audit
Legislative District 13
Congressional District 8
Federal Route Number 9999
Project Length 0.52 mi.
ADT 200
Functional Class Local Access
Type of Work Reconstruction
Project Contact Robert Cousart
Contact Email clerk@cityofkittitas.com
TIB Engineer Jonathan Heusman
Last Payment Date 06/12/2008

Project Schedule

  Target Date Actual Date
Project Selection Date   11/16/2007
Delayed Project Date 07/01/2010  
Predesign Approval
Design Approval 01/01/2008 02/20/2008
Bid Auth. Approval 01/01/2008 02/20/2008
Construction Approval 07/01/2008 02/28/2008
Project Closeout 10/31/2008 06/02/2008
Audit Date   06/12/2008
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 7,799
Construction Contract 112,644 108,937
Other Construction 0 0
Total Construction 112,644 116,736
     
Funding Increase 4,092  
Total TIB Funding 116,736 116,736

Local Funding Partners

Funding Amount Percent
KITTITAS 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

The project consist of base preparation and 2 in overlay of the following segments 2nd Avenue - Mason Street to Pierce Street Okanogan Street - End of Rd to Patrick Avenue 5th Street - Spokane Street to Okanogan Street 7th Street - Spokane Street to Okanogan Street

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments