Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Cle Elum's Overlay Project

2-E-930(001)-1

2-E-930(001)-1
Overlay Project

FY 2007 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $77,770

County: Kittitas   |   Legislative District: 13   |   Project Length: 930.00   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 03/18/2008

Project Information

Lead Agency CLE ELUM
Funding Year 2007
Program SCPP
Current Phase Audit
Legislative District 13
Congressional District 8
Federal Route Number P190
Project Length 930.00 mi.
ADT 1,000
Functional Class Collector
Type of Work Resurfacing
Project Contact Charles Glondo
Contact Email
TIB Engineer Jonathan Heusman
Last Payment Date 03/18/2008

Project Schedule

  Target Date Actual Date
Project Selection Date   01/27/2006
Delayed Project Date 07/01/2008  
Predesign Approval
Design Approval 01/27/2006
Bid Auth. Approval 01/27/2006 01/27/2006
Construction Approval 04/01/2007 05/01/2007
Project Closeout 03/01/2008 03/18/2008
Audit Date   03/18/2008
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 8,956
Construction Contract 76,213 68,814
Other Construction 0 0
Total Construction 76,213 77,770
     
Funding Increase 1,558  
Total TIB Funding 77,770 77,770

Local Funding Partners

Funding Amount Percent
CLE ELUM 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

Small City Preservation Overlay Project W 1st St - I-90 Ramp to Pine St

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments