City of Pomeroy's 2022 Seal Coat Award

2-E-929(005)-1

2-E-929(005)-1
2022 Seal Coat Award

Multiple Locations

FY 2024 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $218,402

County: Garfield   |   Legislative District: 9   |   Project Length: 2.00   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 11/29/2023

Project Information

Lead Agency POMEROY
Funding Year 2024
Program SCPP
Current Phase Audit
Legislative District 9
Congressional District 5
Federal Route Number 9999
Project Length 2.00 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Grant Morgan
Contact Email garfeng@co.garfield.wa.us
TIB Engineer Jonathan Heusman
Last Payment Date 11/29/2023

Project Schedule

  Target Date Actual Date
Project Selection Date   03/28/2023
Delayed Project Date 07/01/2025  
Predesign Approval 03/23/2023
Design Approval 04/30/2023 04/05/2023
Bid Auth. Approval 04/30/2023 04/05/2023
Construction Approval 04/30/2023 04/05/2023
Project Closeout 11/30/2023 11/15/2023
Audit Date   11/29/2023
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 264,769 218,402
Other Construction 0 0
Total Construction 264,769 218,402
     
Funding Surplus - 46,367  
Total TIB Funding 218,402 218,402

Local Funding Partners

Funding Amount Percent
POMEROY 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

Crack Seal, sweeping, fog seal, and chip seal several segments throughout town as well as some Overlay on Hill St. Work to be done by Columbia County.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments