Projects — TIB Project Information
TIB Project Information
City of Pomeroy's FY 2015 Overlay Project
2-E-929(001)-1
2-E-929(001)-1
FY 2015 Overlay Project
Multiple Locations
FY 2015 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $116,779
County: Garfield | Legislative District: 9 | Project Length: 0.20 | TIB Engineer: Jonathan Heusman | Last Payment Date: 10/30/2014
Project Information
Lead Agency | POMEROY |
Funding Year | 2015 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 9 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 0.20 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Kenny Landkammer |
Contact Email | pompubworks@hotmail.com |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 10/30/2014 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2013 | |
Delayed Project Date | 07/01/2016 | |
Predesign Approval | ||
Design Approval | 01/01/2014 | 12/18/2013 |
Bid Auth. Approval | 06/01/2014 | 12/18/2013 |
Construction Approval | 07/01/2014 | 04/25/2014 |
Project Closeout | 12/31/2014 | 12/08/2014 |
Audit Date | 12/16/2014 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 11,000 | 4,350 |
Right of Way | 0 | 0 |
Total Design | 11,000 | 4,350 |
Construction Engineering | 11,000 | 3,884 |
Construction Contract | 177,500 | 108,545 |
Other Construction | 0 | 0 |
Total Construction | 188,500 | 112,429 |
Funding Surplus | - 82,721 | |
Total TIB Funding | 116,779 | 116,779 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
POMEROY | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
Grind sections and place three-inch overlay.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |