TIB Project Information

Town of Uniontown's 2023 Otta Seal

2-E-920(002)-1

2-E-920(002)-1
2023 Otta Seal

Multiple Locations

FY 2024 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $552,361

County: Whitman   |   Legislative District: 9   |   Project Length: 2.31   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 09/11/2024

Project Information

Lead Agency UNIONTOWN
Funding Year 2024
Program SCPP
Current Phase Audit
Legislative District 9
Congressional District 5
Federal Route Number 9999
Project Length 2.31 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Wesley Kerr
Contact Email wesleykerr@uniontownwa.org
TIB Engineer Jonathan Heusman
Last Payment Date 09/11/2024

Project Schedule

  Target Date Actual Date
Project Selection Date   05/19/2023
Delayed Project Date 07/01/2025  
Predesign Approval
Design Approval 05/22/2023 04/25/2023
Bid Auth. Approval 01/15/2024 02/12/2024
Construction Approval 04/30/2024 04/24/2024
Project Closeout 08/31/2024 09/10/2024
Audit Date   09/11/2024
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 21,500 18,205
Right of Way 0 0
Total Design 21,500 18,205
     
Construction Engineering 21,500 23,793
Construction Contract 407,000 510,363
Other Construction 0 0
Total Construction 428,500 534,156
     
Funding Increase 102,361  
Total TIB Funding 552,361 552,361

Local Funding Partners

Funding Amount Percent
UNIONTOWN 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

Design, construction, and mapping of Otta Seal treatment on all of the Cities gravel roads.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments