City has approximately 2.31 miles of gravel roadway in their system.
Projects — TIB Project Information
TIB Project Information
Town of Uniontown's 2023 Otta Seal
2-E-920(002)-1
2-E-920(002)-1
2023 Otta Seal
Multiple Locations
FY 2024 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $552,361
County: Whitman | Legislative District: 9 | Project Length: 2.31 | TIB Engineer: Jonathan Heusman | Last Payment Date: 09/11/2024
Project Information
Lead Agency | UNIONTOWN |
Funding Year | 2024 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 9 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 2.31 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Wesley Kerr |
Contact Email | wesleykerr@uniontownwa.org |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 09/11/2024 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 05/19/2023 | |
Delayed Project Date | 07/01/2025 | |
Predesign Approval | ||
Design Approval | 05/22/2023 | 04/25/2023 |
Bid Auth. Approval | 01/15/2024 | 02/12/2024 |
Construction Approval | 04/30/2024 | 04/24/2024 |
Project Closeout | 08/31/2024 | 09/10/2024 |
Audit Date | 09/11/2024 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 21,500 | 18,205 |
Right of Way | 0 | 0 |
Total Design | 21,500 | 18,205 |
Construction Engineering | 21,500 | 23,793 |
Construction Contract | 407,000 | 510,363 |
Other Construction | 0 | 0 |
Total Construction | 428,500 | 534,156 |
Funding Increase | 102,361 | |
Total TIB Funding | 552,361 | 552,361 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
UNIONTOWN | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
Design, construction, and mapping of Otta Seal treatment on all of the Cities gravel roads.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |