TIB Project Information

Town of Uniontown's 2022 Seal Coat Award

2-E-920(001)-1

2-E-920(001)-1
2022 Seal Coat Award

Multiple Locations

FY 2024 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $48,051

County: Whitman   |   Legislative District: 9   |   Project Length: 1.01   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 09/16/2024

Project Information

Lead Agency UNIONTOWN
Funding Year 2024
Program SCPP
Current Phase Audit
Legislative District 9
Congressional District 5
Federal Route Number 9999
Project Length 1.01 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Wesley Kerr
Contact Email wesleykerr@uniontownwa.org
TIB Engineer Jonathan Heusman
Last Payment Date 09/16/2024

Project Schedule

  Target Date Actual Date
Project Selection Date   12/02/2022
Delayed Project Date 07/01/2025  
Predesign Approval
Design Approval 02/28/2023 02/09/2023
Bid Auth. Approval 04/30/2023 02/09/2023
Construction Approval 05/15/2023 03/26/2024
Project Closeout 10/31/2024 10/07/2024
Audit Date   10/15/2024
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 17,287 0
Right of Way 0 0
Total Design 17,287 0
     
Construction Engineering 17,287 3,030
Construction Contract 190,179 42,971
Other Construction 0 2,050
Total Construction 207,466 48,051
     
Funding Increase 0  
Funding Surplus - 176,702  
Total TIB Funding 48,051 48,051

Local Funding Partners

Funding Amount Percent
UNIONTOWN 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

Chip Seal of the following segments Union Avenue - Blair St to Church St Church Street - Main St to Railroad Ave Railroad Avenue - Woodwoth St to Church St Washington Street - Spring St to Woodworth St Church Street - Montgomery St to Boniface St Woodworth Street - Boniface St to Montgomery St Spring Street - Montgomery St to Washington St Denison Street - Union Ave to Railroad Ave

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.