Projects — TIB Project Information
TIB Project Information
Town of Rosalia's FY 2012 Overlay Project
2-E-917(001)-1
2-E-917(001)-1
FY 2012 Overlay Project
Multiple Locations
FY 2012 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $116,973
County: Whitman | Legislative District: 9 | Project Length: 0.42 | TIB Engineer: Jonathan Heusman | Last Payment Date: 01/20/2012
Project Information
Lead Agency | ROSALIA |
Funding Year | 2012 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 9 |
Congressional District | 5 |
Federal Route Number | X383 |
Project Length | 0.42 mi. |
ADT | 150 |
Functional Class | Collector |
Type of Work | Resurfacing |
Project Contact | Jim Stenhouse |
Contact Email | mayor@townofrosalia.org |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 01/20/2012 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/19/2010 | |
Delayed Project Date | 07/01/2013 | |
Predesign Approval | ||
Design Approval | 12/15/2010 | 02/03/2011 |
Bid Auth. Approval | 07/01/2011 | 02/03/2011 |
Construction Approval | 08/19/2011 | 08/22/2011 |
Project Closeout | 12/31/2011 | 01/10/2012 |
Audit Date | 01/20/2012 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 7,256 |
Right of Way | 0 | 0 |
Total Design | 0 | 7,256 |
Construction Engineering | 0 | 4,623 |
Construction Contract | 99,138 | 105,094 |
Other Construction | 0 | 0 |
Total Construction | 99,138 | 109,717 |
Funding Increase | 17,835 | |
Total TIB Funding | 116,973 | 116,973 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
ROSALIA | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
This project will repair areas of base failure with digouts, prelevel, crack seal and overlay Whitman Avenue between Second Avnue and North Inland Empire Hwy Loop with a 2-inch overlay.
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |