The PCR ratings for the selected segments are as follows F Street - Church St to Alder St 54 F Street - Alder St to Cannon St 59 H Street - Main St to Alder St 77 Union St - Palouse Cove Rd to Wall St 68
Projects — TIB Project Information
TIB Project Information
City of Palouse's FY 2014 Seal Coat Project
2-E-916(005)-1
2-E-916(005)-1
FY 2014 Seal Coat Project
Multiple Locations
FY 2014 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $18,511
County: Whitman | Legislative District: 9 | Project Length: 0.62 | TIB Engineer: Jonathan Heusman | Last Payment Date: 12/02/2013
Project Information
Lead Agency | PALOUSE |
Funding Year | 2014 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 9 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 0.62 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Dwayne Griffin |
Contact Email | cityclerk@palouse.com |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 12/02/2013 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/16/2012 | |
Delayed Project Date | 07/01/2015 | |
Predesign Approval | ||
Design Approval | 01/01/2013 | 01/22/2013 |
Bid Auth. Approval | 06/01/2013 | 01/22/2013 |
Construction Approval | 07/01/2013 | 07/01/2013 |
Project Closeout | 10/31/2013 | 11/07/2013 |
Audit Date | 12/02/2013 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 4,645 | 0 |
Right of Way | 0 | 0 |
Total Design | 4,645 | 0 |
Construction Engineering | 2,323 | 1,523 |
Construction Contract | 39,483 | 15,226 |
Other Construction | 0 | 1,762 |
Total Construction | 41,806 | 18,511 |
Funding Surplus | - 27,940 | |
Total TIB Funding | 18,511 | 18,511 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
PALOUSE | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
Crack and chip seal sections
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |