Town of Oakesdale's FY 2020 Rehabilitation Project

2-E-915(004)-1

2-E-915(004)-1
FY 2020 Rehabilitation Project

Multiple Locations

FY 2020 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $262,132

County: Whitman   |   Legislative District: 9   |   Project Length: 0.19   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 11/02/2020

Project Information

Lead Agency OAKESDALE
Funding Year 2020
Program SCPP
Current Phase Audit
Legislative District 9
Congressional District 5
Federal Route Number 9999
Project Length 0.19 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Dennis Palmer
Contact Email townofoakesdale@msn.com
TIB Engineer Jonathan Heusman
Last Payment Date 11/02/2020

Project Schedule

  Target Date Actual Date
Project Selection Date   11/16/2018
Delayed Project Date 07/01/2021  
Predesign Approval
Design Approval 01/01/2019 12/05/2018
Bid Auth. Approval 12/31/2019 11/07/2019
Construction Approval 02/29/2020 03/05/2020
Project Closeout 12/31/2020 10/24/2020
Audit Date   11/02/2020
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 44,758 43,999
Right of Way 0 0
Total Design 44,758 43,999
     
Construction Engineering 31,970 22,746
Construction Contract 252,769 199,392
Other Construction 0 0
Total Construction 284,739 222,138
     
Funding Increase 25,629  
Funding Surplus - 92,994  
Total TIB Funding 262,132 266,137

Local Funding Partners

Funding Amount Percent
OAKESDALE 0 0.0%
WSDOT Funding 0 0.0%
Motley Motley  4,005 1.5%
 
 
 
 
 
 
 
Total Local Funding 4,005 2.6%

Project Description

The project provides full depth reclamation (FDR) and two-inch overlay of the approved segments.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.