The existing stairway is in a deteriorated state. The concrete is cracked and buckled. Hand rails are broken. The facility is not ADA accessible.
Projects — TIB Project Information
TIB Project Information
Town of Oakesdale's First Street Walkway
2-E-915(001)-1
2-E-915(001)-1
First Street Walkway
Pearl Ave to Steptoe Ave
FY 2008 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $297,882
County: Whitman | Legislative District: 9 | Project Length: 0.19 | TIB Engineer: Jonathan Heusman | Last Payment Date: 12/10/2008
Project Information
Lead Agency | OAKESDALE |
Funding Year | 2008 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 9 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 0.19 mi. |
ADT | 500 |
Functional Class | Collector |
Type of Work | Reconstruction |
Project Contact | Russell Rickett |
Contact Email | townofoakesdale@msn.com |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 12/10/2008 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 01/26/2007 | |
Delayed Project Date | 07/01/2009 | |
Predesign Approval | ||
Design Approval | 01/26/2007 | 01/26/2007 |
Bid Auth. Approval | 04/01/2007 | 04/11/2007 |
Construction Approval | 04/21/2008 | 04/24/2008 |
Project Closeout | 12/31/2008 | 12/08/2008 |
Audit Date | 12/10/2008 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 31,450 | 33,750 |
Right of Way | 0 | 0 |
Total Design | 31,450 | 33,750 |
Construction Engineering | 34,070 | 31,439 |
Construction Contract | 262,080 | 227,495 |
Other Construction | 0 | 5,198 |
Total Construction | 296,150 | 264,132 |
Funding Increase | 11,663 | |
Funding Surplus | - 41,381 | |
Total TIB Funding | 297,882 | 297,882 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
OAKESDALE | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
The projects removes the existing pedestrian stairway and constructs an ADA compliant walkway. The walkway begins at the bottom of the hill on First St and continues uphill to the school complex on Pearl Ave.
Existing Condition
Project Benefits
- Provides ADA access;
- Creates safe school walk route
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |