Town of LaCrosse's 2007 Overlay Project

2-E-912(002)-1

2-E-912(002)-1
2007 Overlay Project

3rd Street & Leslie Avenue

FY 2008 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $61,454

County: Whitman   |   Legislative District: 9   |   Project Length: 0.46   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 04/07/2008

Project Information

Lead Agency LACROSSE
Funding Year 2008
Program SCPP
Current Phase Audit
Legislative District 9
Congressional District 5
Federal Route Number 9999
Project Length 0.46 mi.
ADT 300
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Angela Broeckel
Contact Email lacrosse@pionnet.com
TIB Engineer Jonathan Heusman
Last Payment Date 04/07/2008

Project Schedule

  Target Date Actual Date
Project Selection Date   05/29/2007
Delayed Project Date 07/01/2009  
Predesign Approval
Design Approval 05/29/2007 05/29/2007
Bid Auth. Approval 05/29/2007 05/29/2007
Construction Approval 06/01/2007 06/01/2007
Project Closeout 03/01/2008 04/07/2008
Audit Date   04/07/2008
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 1,095
Construction Contract 65,000 56,553
Other Construction 0 3,805
Total Construction 65,000 61,454
     
Funding Surplus - 3,546  
Total TIB Funding 61,454 61,454

Local Funding Partners

Funding Amount Percent
LACROSSE 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

The project provides a 2-in overlay of 3rd Street - West City Limits to Leslie Avenue 3rd Street - Leslie Avenue to Crystal Avenue and Leslie Avenue - West City Limits to 3rd Street.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.