Town of Garfield's 2022 Maintenance Project
2-E-911(010)-1
2-E-911(010)-1
2022 Maintenance Project
Multiple Locations
FY 2024 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $6,460
County: Whitman | Legislative District: 9 | Project Length: 3,600.00 | TIB Engineer: Jonathan Heusman | Last Payment Date: 09/27/2023
Project Information
Lead Agency | GARFIELD |
Funding Year | 2024 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 9 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 3600.00 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Shon Clark |
Contact Email | garpublicworks@garfield-wa.com |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 09/27/2023 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/02/2022 | |
Delayed Project Date | 07/01/2025 | |
Predesign Approval | ||
Design Approval | 01/30/2023 | 02/27/2023 |
Bid Auth. Approval | 05/31/2023 | 02/27/2023 |
Construction Approval | 06/30/2023 | 02/27/2023 |
Project Closeout | 10/30/2023 | 10/17/2023 |
Audit Date | 10/16/2023 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 10,675 | 6,460 |
Other Construction | 0 | 0 |
Total Construction | 10,675 | 6,460 |
Funding Surplus | - 4,215 | |
Total TIB Funding | 6,460 | 6,460 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
GARFIELD | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
Crack Sealing and Patching.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |