Town of Garfield's 2022 Seal Coat Award

2-E-911(009)-1

2-E-911(009)-1
2022 Seal Coat Award

Multiple Locations

FY 2024 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $40,929

County: Whitman   |   Legislative District: 9   |   Project Length: 0.54   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 09/27/2023

Project Information

Lead Agency GARFIELD
Funding Year 2024
Program SCPP
Current Phase Audit
Legislative District 9
Congressional District 5
Federal Route Number 9999
Project Length 0.54 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Shon Clark
Contact Email garpublicworks@completebbs.com
TIB Engineer Jonathan Heusman
Last Payment Date 09/27/2023

Project Schedule

  Target Date Actual Date
Project Selection Date   12/02/2022
Delayed Project Date 07/01/2025  
Predesign Approval
Design Approval 02/01/2023 01/13/2023
Bid Auth. Approval 05/01/2024 01/13/2023
Construction Approval 06/01/2024 01/13/2023
Project Closeout 11/01/2024 10/17/2023
Audit Date   10/16/2023
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 5,300 0
Right of Way 0 0
Total Design 5,300 0
     
Construction Engineering 5,300 0
Construction Contract 64,544 40,929
Other Construction 0 0
Total Construction 69,844 40,929
     
Funding Surplus - 34,215  
Total TIB Funding 40,929 40,929

Local Funding Partners

Funding Amount Percent
GARFIELD 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

Double Chip seal and Fog seal completed by Whitman County. Prep work to be completed by the Town. California Street - 4th St to 8th St Adams Street - 7th St to 10th St Main Street - 4th St to 8th St

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.