The existing surface is showing signs of wear. The current Pavement Condition Rating is 50 caused by localized alligator cracking and patching.
Projects — TIB Project Information
TIB Project Information
Town of Garfield's FY 2013 Overlay Project
2-E-911(006)-1
2-E-911(006)-1
FY 2013 Overlay Project
Multiple Locations
FY 2013 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $67,524
County: Whitman | Legislative District: 9 | Project Length: 0.05 | TIB Engineer: Jonathan Heusman | Last Payment Date: 04/01/2013
Project Information
Lead Agency | GARFIELD |
Funding Year | 2013 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 9 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 0.05 mi. |
ADT | 150 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Annie Pillers |
Contact Email | garfield-town@completebbs.com |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 04/01/2013 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/18/2011 | |
Delayed Project Date | 07/01/2014 | |
Predesign Approval | ||
Design Approval | 01/01/2012 | 12/13/2011 |
Bid Auth. Approval | 05/01/2012 | 12/13/2011 |
Construction Approval | 06/07/2012 | 06/08/2012 |
Project Closeout | 01/31/2013 | 03/22/2013 |
Audit Date | 04/01/2013 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 7,260 | 6,272 |
Right of Way | 0 | 0 |
Total Design | 7,260 | 6,272 |
Construction Engineering | 0 | 1,107 |
Construction Contract | 49,871 | 60,145 |
Other Construction | 0 | 0 |
Total Construction | 49,871 | 61,252 |
Funding Increase | 11,332 | |
Funding Surplus | - 939 | |
Total TIB Funding | 67,524 | 67,524 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
GARFIELD | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
The project grinds the section to remove excessive slope, digs out alligatored areas, crack seals where needed and applies a two-in overlay. Upgrade of four ramps ensures ADA compliance.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |