The existing roadways show transverse and longitudinal cracking with minor areas of alligator cracking. The pavement condition rating (PCR) for 3rd is 68. The PCR for 4th is 63.
Projects — TIB Project Information
TIB Project Information
Town of Garfield's FY 2012 Seal Coat Project
2-E-911(005)-1
2-E-911(005)-1
FY 2012 Seal Coat Project
Multiple Locations
FY 2012 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $23,706
County: Whitman | Legislative District: 9 | Project Length: 0.36 | TIB Engineer: Jonathan Heusman | Last Payment Date: 11/02/2011
Project Information
Lead Agency | GARFIELD |
Funding Year | 2012 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 9 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 0.36 mi. |
ADT | 150 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Annie Pillers |
Contact Email | garfield-town@completebbs.com |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 11/02/2011 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/19/2010 | |
Delayed Project Date | 07/01/2013 | |
Predesign Approval | ||
Design Approval | 12/15/2010 | 01/21/2011 |
Bid Auth. Approval | 06/01/2011 | 01/21/2011 |
Construction Approval | 07/01/2011 | 07/11/2011 |
Project Closeout | 09/30/2011 | 10/26/2011 |
Audit Date | 11/02/2011 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 24,797 | 23,706 |
Other Construction | 0 | 0 |
Total Construction | 24,797 | 23,706 |
Funding Surplus | - 1,091 | |
Total TIB Funding | 23,706 | 23,706 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
GARFIELD | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
The project chip seals the following two segments 3rd Street between Main St and Cleveland St 4th Street between Jefferson St and Cleveland St Prep work includes removing areas with base failure and crack sealing the sections. The project improves 1,918 feet of the town's street system.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |