TIB Project Information

Town of Farmington's 2024 Otta Seal

2-E-910(002)-1

2-E-910(002)-1
2024 Otta Seal

Multiple Locations

FY 2025 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $664,166

County: Whitman   |   Legislative District: 9   |   Project Length: 1.30   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 09/13/2024

Project Information

Lead Agency FARMINGTON
Funding Year 2025
Program SCPP
Current Phase Audit
Legislative District 9
Congressional District 5
Federal Route Number 9999
Project Length 1.30 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Beth Anderson
Contact Email townoffarmington.wa@gmail.com
TIB Engineer Jonathan Heusman
Last Payment Date 09/13/2024

Project Schedule

  Target Date Actual Date
Project Selection Date   10/17/2023
Delayed Project Date 07/01/2026  
Predesign Approval
Design Approval 10/20/2023 10/20/2023
Bid Auth. Approval 03/31/2024 03/11/2024
Construction Approval 04/30/2024 04/16/2024
Project Closeout 12/31/2024 09/05/2024
Audit Date   09/13/2024
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 25,000 24,992
Right of Way 0 0
Total Design 25,000 24,992
     
Construction Engineering 25,000 52,008
Construction Contract 600,000 587,166
Other Construction 0 0
Total Construction 625,000 639,174
     
Funding Increase 72,645  
Funding Surplus - 58,479  
Total TIB Funding 664,166 664,166

Local Funding Partners

Funding Amount Percent
FARMINGTON 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

Otta Seal on existing gravel and paved streets.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments