D Street between Banta Street (5th) and 4th Street is 24 feet wide with a pavement condition rating (PCR) of 42. The section between 4th Street and 3rd Street is 45 feet wide with a PCR of 77.
Projects — TIB Project Information
TIB Project Information
Town of Endicott's FY 2015 Seal Coat Project
2-E-909(002)-1
2-E-909(002)-1
FY 2015 Seal Coat Project
Multiple Locations
FY 2015 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $12,109
County: Whitman | Legislative District: 9 | Project Length: 0.25 | TIB Engineer: Jonathan Heusman | Last Payment Date: 11/17/2014
Project Information
Lead Agency | ENDICOTT |
Funding Year | 2015 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 9 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 0.25 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Sue Bafus |
Contact Email | townofendicott@stjohncable.com |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 11/17/2014 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2013 | |
Delayed Project Date | 07/01/2016 | |
Predesign Approval | ||
Design Approval | 01/01/2014 | 01/06/2014 |
Bid Auth. Approval | 06/01/2014 | 01/06/2014 |
Construction Approval | 07/01/2014 | 01/06/2014 |
Project Closeout | 12/31/2014 | 11/07/2014 |
Audit Date | 11/17/2014 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 24,669 | 12,109 |
Other Construction | 0 | 0 |
Total Construction | 24,669 | 12,109 |
Funding Surplus | - 12,560 | |
Total TIB Funding | 12,109 | 12,109 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
ENDICOTT | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
The project seals cracks and chip seals the surface on D Street between Banta Street and 3rd Street.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |