TIB Project Information
Town of Colton's FY 2021 Seal Coat Project
2-E-908(003)-1
2-E-908(003)-1
FY 2021 Seal Coat Project
Multiple Locations
FY 2021 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $50,138
County: Whitman | Legislative District: 9 | Project Length: 1.13 | TIB Engineer: Jonathan Heusman | Last Payment Date: 11/02/2020
Project Information
Lead Agency | COLTON |
Funding Year | 2021 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 9 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 1.13 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Jenni Straghan |
Contact Email | coltontownhall@hotmail.com |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 11/02/2020 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2019 | |
Delayed Project Date | 07/01/2022 | |
Predesign Approval | ||
Design Approval | 02/01/2020 | 12/11/2019 |
Bid Auth. Approval | 06/01/2020 | 12/11/2019 |
Construction Approval | 06/30/2020 | 12/11/2019 |
Project Closeout | 10/31/2020 | 10/27/2020 |
Audit Date | 11/02/2020 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 90,388 | 46,583 |
Other Construction | 0 | 5,484 |
Total Construction | 90,388 | 52,067 |
Funding Surplus | - 40,250 | |
Total TIB Funding | 50,138 | 52,067 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
COLTON | 1,929 | 3.7% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 1,929 | 3.7% |
Project Description
Chip seal multiple segments.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |