Front Street is the main east-west street through Albion. From the east, Front is the continuation of the Pullman-Albion Road. It serves the post office and ties into Albion Road, the route to SR 195. The pavement surface is crack sealed but ready for treatment. The current pavement condition rating is 68.
Projects — TIB Project Information
TIB Project Information
Town of Albion's FY 2017 Seal Coat Project
2-E-907(002)-1
2-E-907(002)-1
FY 2017 Seal Coat Project
Multiple Locations
FY 2017 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $22,962
County: Whitman | Legislative District: 9 | Project Length: 0.57 | TIB Engineer: Jonathan Heusman | Last Payment Date: 12/23/2016
Project Information
Lead Agency | ALBION |
Funding Year | 2017 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 9 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 0.57 mi. |
ADT | 150 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Kenneth G. Smith |
Contact Email | albionpublicwks@palouse.com |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 12/23/2016 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/20/2015 | |
Delayed Project Date | 07/01/2018 | |
Predesign Approval | ||
Design Approval | 01/15/2016 | 12/08/2015 |
Bid Auth. Approval | 04/01/2016 | 12/08/2015 |
Construction Approval | 05/01/2016 | 02/01/2016 |
Project Closeout | 03/01/2017 | 02/17/2017 |
Audit Date | 02/17/2017 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 4,768 | 0 |
Right of Way | 0 | 0 |
Total Design | 4,768 | 0 |
Construction Engineering | 0 | 1,938 |
Construction Contract | 50,069 | 19,383 |
Other Construction | 0 | 1,641 |
Total Construction | 50,069 | 22,962 |
Funding Surplus | - 31,875 | |
Total TIB Funding | 22,962 | 22,962 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
ALBION | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
This project finishes crack sealing Front Street from H street to the east city limit. Whitman County agreed to provide chip seal of the street.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |