Town of Northport's FY 2021 Seal Coat Project
2-E-905(003)-1
2-E-905(003)-1
FY 2021 Seal Coat Project
Multiple Locations
FY 2021 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $131,029
County: Stevens | Legislative District: 7 | Project Length: 1.14 | TIB Engineer: Andrew Beagle | Last Payment Date: 10/29/2020
Project Information
Lead Agency | NORTHPORT |
Funding Year | 2021 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 7 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 1.14 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Karen Baribault |
Contact Email | townofnorthport@plix.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | 10/29/2020 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2019 | |
Delayed Project Date | 07/01/2022 | |
Predesign Approval | ||
Design Approval | 02/01/2020 | 12/17/2019 |
Bid Auth. Approval | 05/01/2020 | 02/27/2020 |
Construction Approval | 05/31/2020 | 04/17/2020 |
Project Closeout | 10/31/2020 | 09/29/2020 |
Audit Date | 10/29/2020 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 10,256 | 9,007 |
Right of Way | 0 | 0 |
Total Design | 10,256 | 9,007 |
Construction Engineering | 10,248 | 9,827 |
Construction Contract | 136,724 | 112,195 |
Other Construction | 0 | 0 |
Total Construction | 146,972 | 122,022 |
Funding Increase | 2,226 | |
Funding Surplus | - 28,425 | |
Total TIB Funding | 131,029 | 131,029 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
NORTHPORT | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
The project provides double chip seal and fog seal of the approved segments.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |