City of Kettle Falls's FY 2019 Seal Coat Project

2-E-903(003)-1

2-E-903(003)-1
FY 2019 Seal Coat Project

Multiple Locations

FY 2019 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $178,230

County: Stevens   |   Legislative District: 7   |   Project Length: 1.22   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 10/25/2019

Project Information

Lead Agency KETTLE FALLS
Funding Year 2019
Program SCPP
Current Phase Audit
Legislative District 7
Congressional District 5
Federal Route Number 9999
Project Length 1.22 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Dave Willey
Contact Email dwilley@kettle-falls.com
TIB Engineer Andrew Beagle
Last Payment Date 10/25/2019

Project Schedule

  Target Date Actual Date
Project Selection Date   11/17/2017
Delayed Project Date 07/01/2020  
Predesign Approval
Design Approval 01/01/2018 02/07/2018
Bid Auth. Approval 03/01/2018 02/07/2018
Construction Approval 06/01/2018 06/14/2018
Project Closeout 09/01/2019 07/25/2019
Audit Date   10/25/2019
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 24,571
Right of Way 10,000 0
Total Design 10,000 24,571
     
Construction Engineering 0 0
Construction Contract 92,167 153,658
Other Construction 0 0
Total Construction 92,167 153,658
     
Funding Increase 104,304  
Funding Surplus - 28,241  
Total TIB Funding 178,230 178,229

Local Funding Partners

Funding Amount Percent
KETTLE FALLS 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

The project repairs pavement, seals cracks and chip seals the following streets 6th St - Juniper to E End Kalmia St - 10th to 4th Larch St - 8th to 4th

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments