City of Spangle's Crack Seal and Pavement Repair PILOT

2-E-899(003)-1

2-E-899(003)-1
Crack Seal and Pavement Repair PILOT

City Wide

FY 2019 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $14,683

County: Spokane   |   Legislative District: 9   |   Project Length: 0.10   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 06/30/2020

Project Information

Lead Agency SPANGLE
Funding Year 2019
Program SCPP
Current Phase Audit
Legislative District 9
Congressional District 5
Federal Route Number 9999
Project Length 0.10 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Study
Project Contact Peggy Mangis
Contact Email townofspangle@centurytel.net
TIB Engineer Andrew Beagle
Last Payment Date 06/30/2020

Project Schedule

  Target Date Actual Date
Project Selection Date   10/07/2019
Delayed Project Date 07/01/2022  
Predesign Approval 10/07/2019
Design Approval 11/18/2019 11/18/2019
Bid Auth. Approval 04/01/2020 03/01/2020
Construction Approval 05/01/2020 04/28/2020
Project Closeout 10/31/2020 06/25/2020
Audit Date   06/30/2020
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 4,377 4,377
Total Predesign 4,377 4,377
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 2,718
Construction Contract 0 7,587
Other Construction 0 0
Total Construction 0 10,305
     
Funding Increase 10,306  
Total TIB Funding 14,683 14,682

Local Funding Partners

Funding Amount Percent
SPANGLE -1 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding -1 0.0%

Project Description

Evaluation to crack seal and provide pavement repair prior to larger maintenance project.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.