The existing streets are worn with some deterioration. The current pavement condition ratings are Stringham - First to NC/L63 Sprague - Lake to Emma54 Sprague - Emma to Stringham68 Third St - Lake to Emma68
Projects — TIB Project Information
TIB Project Information
Town of Rockford's FY 2020 Seal Coat Project
2-E-898(003)-1
2-E-898(003)-1
FY 2020 Seal Coat Project
Multiple Locations
FY 2020 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $85,231
County: Spokane | Legislative District: 9 | Project Length: 0.84 | TIB Engineer: Andrew Beagle | Last Payment Date: 01/14/2021
Project Information
Lead Agency | ROCKFORD |
Funding Year | 2020 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 9 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 0.84 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Dave Thompson |
Contact Email | publicworks@rockfordwa.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | 01/14/2021 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/16/2018 | |
Delayed Project Date | 07/01/2021 | |
Predesign Approval | ||
Design Approval | 01/01/2019 | 01/11/2019 |
Bid Auth. Approval | 01/01/2019 | 01/11/2019 |
Construction Approval | 02/01/2019 | 01/11/2019 |
Project Closeout | 03/31/2021 | 03/03/2021 |
Audit Date | 03/15/2021 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 4,250 |
Construction Contract | 98,728 | 74,168 |
Other Construction | 0 | 6,813 |
Total Construction | 98,728 | 85,231 |
Funding Increase | 0 | |
Funding Surplus | - 13,497 | |
Total TIB Funding | 85,231 | 85,231 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
ROCKFORD | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
The project provides prelevel, pavement repair, crack seal and chip seal of the approved segments.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |