Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

Town of Rockford's FY 2020 Seal Coat Project

2-E-898(003)-1

2-E-898(003)-1
FY 2020 Seal Coat Project

Multiple Locations

FY 2020 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $85,231

County: Spokane   |   Legislative District: 9   |   Project Length: 0.84   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 01/14/2021

Project Information

Lead Agency ROCKFORD
Funding Year 2020
Program SCPP
Current Phase Audit
Legislative District 9
Congressional District 5
Federal Route Number 9999
Project Length 0.84 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Dave Thompson
Contact Email publicworks@rockfordwa.com
TIB Engineer Andrew Beagle
Last Payment Date 01/14/2021

Project Schedule

  Target Date Actual Date
Project Selection Date   11/16/2018
Delayed Project Date 07/01/2021  
Predesign Approval
Design Approval 01/01/2019 01/11/2019
Bid Auth. Approval 01/01/2019 01/11/2019
Construction Approval 02/01/2019 01/11/2019
Project Closeout 03/31/2021 03/03/2021
Audit Date   03/15/2021
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 4,250
Construction Contract 98,728 74,168
Other Construction 0 6,813
Total Construction 98,728 85,231
     
Funding Increase 0  
Funding Surplus - 13,497  
Total TIB Funding 85,231 85,231

Local Funding Partners

Funding Amount Percent
ROCKFORD 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

The project provides prelevel, pavement repair, crack seal and chip seal of the approved segments.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments