The existing surface is extremely deteriorated with medium to high alligator cracking. The street serves as a oversize load bypass route for SR 27.
Projects — TIB Project Information
TIB Project Information
Town of Rockford's Missile Base Road
2-E-898(002)-1
2-E-898(002)-1
Missile Base Road
SR 27 to Emma Street (SR 278)
FY 2016 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $218,939
County: Spokane | Legislative District: 9 | Project Length: 0.38 | TIB Engineer: Andrew Beagle | Last Payment Date: 04/05/2017
Project Information
Lead Agency | ROCKFORD |
Funding Year | 2016 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 9 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 0.38 mi. |
ADT | 200 |
Functional Class | Local Access |
Type of Work | Resurfacing |
Project Contact | Heidi Johnson |
Contact Email | townclerk@rockfordwa.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | 04/05/2017 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 06/28/2016 | |
Delayed Project Date | 07/01/2018 | |
Predesign Approval | ||
Design Approval | 06/28/2016 | 07/25/2016 |
Bid Auth. Approval | 08/01/2016 | 07/25/2016 |
Construction Approval | 08/24/2016 | 08/29/2016 |
Project Closeout | 06/01/2017 | 08/03/2017 |
Audit Date | 08/03/2017 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 9,844 | 20,489 |
Right of Way | 0 | 0 |
Total Design | 9,844 | 20,489 |
Construction Engineering | 19,688 | 9,914 |
Construction Contract | 216,564 | 156,670 |
Other Construction | 13,604 | 31,867 |
Total Construction | 249,856 | 198,450 |
Funding Surplus | - 40,761 | |
Total TIB Funding | 218,939 | 218,939 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
ROCKFORD | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
The project pulverizes the existing pavement into the base, reshapes the base, places crushed surfacing top course and a three-inch HMA cap to a width of 22 feet. County forces will place shoulder rock and replace existing deteriorated culverts.
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |