The surfaces on the following segments are deteriorated and in need of treatment. Their current pavement condition ratings are 41 - Howard Street - 4th Street to Brooks Road 45 - Spence Street - Washington Street to Hallett Street 40 - Broad Street - Lake Street to Barker Street 50 - Sherman Avenue - Barker Street to City Limits
Projects — TIB Project Information
TIB Project Information
City of Medical Lake's FY 2017 Overlay Project
2-E-897(004)-1
2-E-897(004)-1
FY 2017 Overlay Project
Multiple Locations
FY 2017 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $215,766
County: Spokane | Legislative District: 6 | Project Length: 0.72 | TIB Engineer: Andrew Beagle | Last Payment Date: 12/12/2018
Project Information
Lead Agency | MEDICAL LAKE |
Funding Year | 2017 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 6 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 0.72 mi. |
ADT | 250 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Doug Ross |
Contact Email | dross@medical-lake.org |
TIB Engineer | Andrew Beagle |
Last Payment Date | 12/12/2018 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/20/2015 | |
Delayed Project Date | 07/01/2018 | |
Predesign Approval | ||
Design Approval | 01/15/2016 | 03/09/2016 |
Bid Auth. Approval | 06/01/2018 | 06/01/2018 |
Construction Approval | 07/01/2018 | 08/28/2018 |
Project Closeout | 12/31/2018 | 12/06/2018 |
Audit Date | 12/12/2018 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 39,900 | 12,035 |
Right of Way | 0 | 0 |
Total Design | 39,900 | 12,035 |
Construction Engineering | 0 | 12,079 |
Construction Contract | 174,973 | 153,046 |
Other Construction | 0 | 49,963 |
Total Construction | 174,973 | 215,088 |
Funding Increase | 36,690 | |
Funding Surplus | - 35,797 | |
Total TIB Funding | 215,766 | 227,123 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
MEDICAL LAKE | 11,357 | 5.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 11,357 | 5.0% |
Project Description
This project seals cracks, repairs pavement and overlays the following segments. The scope includes updating four ADA ramps to the current standard. - Howard Street - 4th Street to Brooks Road - Spence Street - Washington Street to Hallett Street - Broad Street - Lake Street to Barker Street - Sherman Avenue - Barker Street to City Limits
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |