Brooks Road provides access to the central business district and Eastern State Hospital campus from SR 2. Alligator cracking and some rutting is present along the outside wheel tracks. The city repaired the alligatored areas in many locations. The current pavement condition rating is 45.
Projects — TIB Project Information
TIB Project Information
City of Medical Lake's FY 2015 Overlay Project
2-E-897(003)-1
2-E-897(003)-1
FY 2015 Overlay Project
Multiple Locations
FY 2015 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $216,948
County: Spokane | Legislative District: 6 | Project Length: 0.73 | TIB Engineer: Andrew Beagle | Last Payment Date: 04/01/2015
Project Information
Lead Agency | MEDICAL LAKE |
Funding Year | 2015 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 6 |
Congressional District | 5 |
Federal Route Number | I321 |
Project Length | 0.73 mi. |
ADT | 0 |
Functional Class | Collector |
Type of Work | Resurfacing |
Project Contact | Doug Ross |
Contact Email | dross@medical-lake.org |
TIB Engineer | Andrew Beagle |
Last Payment Date | 04/01/2015 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2013 | |
Delayed Project Date | 07/01/2016 | |
Predesign Approval | ||
Design Approval | 03/01/2014 | 03/06/2014 |
Bid Auth. Approval | 06/01/2014 | 08/15/2014 |
Construction Approval | 09/15/2014 | 09/09/2014 |
Project Closeout | 02/01/2015 | 03/09/2015 |
Audit Date | 04/01/2015 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 8,302 | 10,980 |
Right of Way | 0 | 0 |
Total Design | 8,302 | 10,980 |
Construction Engineering | 12,350 | 11,239 |
Construction Contract | 108,424 | 206,146 |
Other Construction | 0 | 0 |
Total Construction | 120,774 | 217,385 |
Funding Increase | 87,872 | |
Total TIB Funding | 216,948 | 228,365 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
MEDICAL LAKE | 11,417 | 5.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 11,417 | 5.0% |
Project Description
The project seals cracks, repairs areas of alligator cracking and places a hot mix asphalt overlay on Brooks Road between Lefevre (SR 902) and the north city limits.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |