The following streets show wear and are ready for maintenance Pine Street - Market to Harvey Mill Street - Pine to Wood
Projects — TIB Project Information
TIB Project Information
Town of Latah's FY 2018 Seal Coat Project
2-E-896(002)-1
2-E-896(002)-1
FY 2018 Seal Coat Project
Multiple Locations
FY 2018 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $126,009
County: Spokane | Legislative District: 9 | Project Length: 0.65 | TIB Engineer: Andrew Beagle | Last Payment Date: 01/30/2019
Project Information
Lead Agency | LATAH |
Funding Year | 2018 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 9 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 0.65 mi. |
ADT | 200 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Heidi Turnbough |
Contact Email | latahtown@gmail.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | 01/30/2019 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/18/2016 | |
Delayed Project Date | 07/01/2019 | |
Predesign Approval | ||
Design Approval | 01/01/2017 | 12/16/2016 |
Bid Auth. Approval | 04/01/2017 | 12/16/2016 |
Construction Approval | 05/01/2017 | 12/16/2016 |
Project Closeout | 10/31/2018 | 01/07/2019 |
Audit Date | 01/30/2019 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 4,070 | 0 |
Right of Way | 0 | 0 |
Total Design | 4,070 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 50,000 | 126,009 |
Other Construction | 0 | 0 |
Total Construction | 50,000 | 126,009 |
Funding Increase | 71,939 | |
Total TIB Funding | 126,009 | 126,009 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
LATAH | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
The project repairs pavement, seals crack and applies a chip seal to Pine and Mill Streets. Spokane County agreed to complete the work for the town.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |