Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

Town of Fairfield's FY 2017 Overlay Project

2-E-895(002)-1

2-E-895(002)-1
FY 2017 Overlay Project

Multiple Locations

FY 2017 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $181,731

County: Spokane   |   Legislative District: 9   |   Project Length: 0.31   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 01/17/2017

Project Information

Lead Agency FAIRFIELD
Funding Year 2017
Program SCPP
Current Phase Audit
Legislative District 9
Congressional District 5
Federal Route Number 9999
Project Length 0.31 mi.
ADT 150
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Cheryl Loeffler
Contact Email fairfieldwa@outlook.com
TIB Engineer Andrew Beagle
Last Payment Date 01/17/2017

Project Schedule

  Target Date Actual Date
Project Selection Date   11/20/2015
Delayed Project Date 07/01/2018  
Predesign Approval
Design Approval 01/15/2016 12/08/2015
Bid Auth. Approval 04/01/2016 07/01/2016
Construction Approval 08/01/2016 08/01/2016
Project Closeout 12/31/2016 12/28/2016
Audit Date   01/17/2017
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 12,154 12,274
Right of Way 0 0
Total Design 12,154 12,274
     
Construction Engineering 12,154 12,145
Construction Contract 121,523 157,312
Other Construction 0 0
Total Construction 133,677 169,457
     
Funding Increase 35,900  
Total TIB Funding 181,731 181,731

Local Funding Partners

Funding Amount Percent
FAIRFIELD 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

This project pulverizes the surface, adds crushed surfacing and overlays the streets to provide additional structure. Four ADA ramp upgrades and minor sidewalk repair are included in the scope. The project includes work on the following streets - Brewster Street - Railroad to McNeil - Johnson Avenue - Brewster to Main - McNeil Avenue - Governor Moore to Main

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments