The pavement ratings for the segments are as follows Circle Drive W - 1st St to Circle Dr E 48 Circle Drive E - Circle Dr W to 1st St 56
Projects — TIB Project Information
TIB Project Information
City of Newport's FY 2021 Seal Coat Project
2-E-892(004)-1
2-E-892(004)-1
FY 2021 Seal Coat Project
Multiple Locations
FY 2021 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $103,905
County: Pend Oreille | Legislative District: 7 | Project Length: 0.67 | TIB Engineer: Andrew Beagle | Last Payment Date: 10/15/2021
Project Information
Lead Agency | NEWPORT |
Funding Year | 2021 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 7 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 0.67 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Dave North |
Contact Email | pwd@newport-wa.org |
TIB Engineer | Andrew Beagle |
Last Payment Date | 10/15/2021 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2019 | |
Delayed Project Date | 07/01/2022 | |
Predesign Approval | ||
Design Approval | 03/01/2020 | 02/10/2020 |
Bid Auth. Approval | 02/28/2021 | 06/28/2021 |
Construction Approval | 07/15/2021 | 08/06/2021 |
Project Closeout | 10/15/2021 | 09/29/2021 |
Audit Date | 10/15/2021 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 2,400 | 2,400 |
Right of Way | 0 | 0 |
Total Design | 2,400 | 2,400 |
Construction Engineering | 2,400 | 2,400 |
Construction Contract | 103,048 | 104,574 |
Other Construction | 0 | 0 |
Total Construction | 105,448 | 106,974 |
Funding Surplus | - 3,943 | |
Total TIB Funding | 103,905 | 109,374 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
NEWPORT | 5,469 | 5.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 5,469 | 5.0% |
Project Description
The project provides prelevel, pavement repair, crack seal and double chip seal of the approved segment Circle Drive - 1st St to 1st St
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |