Projects — TIB Project Information
TIB Project Information
City of Newport's 2008 WSDOT Chip Seal
2-E-892(001)-1
2-E-892(001)-1
2008 WSDOT Chip Seal
1st Street - Sta 100 to Washington Ave
FY 2008 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $70,468
County: Pend Oreille | Legislative District: 7 | Project Length: 0.87 | TIB Engineer: Andrew Beagle | Last Payment Date: 09/16/2009
Project Information
Lead Agency | NEWPORT |
Funding Year | 2008 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 7 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 0.87 mi. |
ADT | 0 |
Functional Class | Collector |
Type of Work | Resurfacing |
Project Contact | Ray King |
Contact Email | cityofnewport@newport-wa.org |
TIB Engineer | Andrew Beagle |
Last Payment Date | 09/16/2009 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 10/15/2007 | |
Delayed Project Date | 07/01/2010 | |
Predesign Approval | ||
Design Approval | 01/31/2008 | |
Bid Auth. Approval | 01/31/2008 | |
Construction Approval | 03/20/2008 | |
Project Closeout | 12/31/2008 | 08/28/2009 |
Audit Date | 09/16/2009 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 6,637 |
Construction Contract | 61,101 | 63,831 |
Other Construction | 0 | 0 |
Total Construction | 61,101 | 70,468 |
Funding Increase | 9,367 | |
Total TIB Funding | 70,468 | 70,468 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
NEWPORT | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
1st Street - Sta 100 to Washington Avenue Provide chip seal in conjunction with WSDOT pavement maintenance project.
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |