 Projects — TIB Project Information

TIB Project Information

Town of Ione's SR 31 Pedestrian Improvements

2-E-889(005)-1

2-E-889(005)-1
SR 31 Pedestrian Improvements

Multiple Locations

FY 2013 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $142,079

County: Pend Oreille   |   Legislative District: 7   |   Project Length: 2,000.00   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 04/15/2014

Project Information

Lead Agency IONE
Funding Year 2013
Program SCPP
Current Phase Audit
Legislative District 7
Congressional District 0
Federal Route Number 0031
Project Length 2000.00 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Safety
Project Contact Larry Larson, WSDOT PE
Contact Email larsonl@wsdot.wa.gov
TIB Engineer Andrew Beagle
Last Payment Date 04/15/2014

Project Schedule

  Target Date Actual Date
Project Selection Date   11/08/2012
Delayed Project Date 07/01/2015  
Predesign Approval
Design Approval 11/08/2012 11/08/2012
Bid Auth. Approval 02/01/2013 06/06/2013
Construction Approval 02/15/2013 06/06/2013
Project Closeout 03/01/2014 03/28/2014
Audit Date   04/15/2014
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 85,766 101,386
Right of Way 0 0
Total Design 85,766 101,386
     
Construction Engineering 0 110,443
Construction Contract 23,936 454,709
Other Construction 0 0
Total Construction 23,936 565,152
     
Funding Increase 32,377  
Total TIB Funding 142,079 666,537

Local Funding Partners

Funding Amount Percent
IONE 0 0.0%
WSDOT Funding 0 0.0%
Federal Funds  524,458 78.7%
 
 
 
 
 
 
 
Total Local Funding 524,458 78.7%

Project Description

The project reconstructs or adds new sidewalk along SR 31 in Ione. ADA ramps will be upgraded to the current standard. The scope includes crosswalk and shoulder improvements in Metaline and shoulder improvements in Metaline Falls. WSDOT Eastern Region will provide design and construction management for the project under Task Order Agreement No. GCB1310 executed on 9 October 2012.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.