Existing sidewalk is severely cracked and spalled in many areas within the project limits. Tripping hazards are prevalent in the deteriorated areas.
Projects — TIB Project Information
TIB Project Information
Town of Ione's FY 2013 Sidewalk Maintenance Project
2-E-889(004)-1
2-E-889(004)-1
FY 2013 Sidewalk Maintenance Project
Multiple Locations
FY 2013 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $53,192
County: Pend Oreille | Legislative District: 7 | Project Length: 0.15 | TIB Engineer: Andrew Beagle | Last Payment Date: 09/14/2012
Project Information
Lead Agency | IONE |
Funding Year | 2013 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 7 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 0.15 mi. |
ADT | 150 |
Functional Class | TIB Arterial |
Type of Work | Pedestrian |
Project Contact | Sandy Hutchinson |
Contact Email | townclerk@potc.net |
TIB Engineer | Andrew Beagle |
Last Payment Date | 09/14/2012 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/18/2011 | |
Delayed Project Date | 07/01/2014 | |
Predesign Approval | ||
Design Approval | 01/01/2012 | 01/24/2012 |
Bid Auth. Approval | 05/01/2012 | 01/24/2012 |
Construction Approval | 05/16/2012 | 06/06/2012 |
Project Closeout | 10/31/2012 | 08/29/2012 |
Audit Date | 09/14/2012 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 6,450 | 4,612 |
Right of Way | 0 | 0 |
Total Design | 6,450 | 4,612 |
Construction Engineering | 4,900 | 4,900 |
Construction Contract | 38,150 | 43,680 |
Other Construction | 0 | 0 |
Total Construction | 43,050 | 48,580 |
Funding Increase | 3,692 | |
Total TIB Funding | 53,192 | 53,192 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
IONE | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
The project reconstructs sidewalk on the north side of Main Street one half block west to SR 31 and on the south side from SR 31 to 1st Street. Sidewalk ramps will be updated to meet ADA requirements. The scope was reduced at Bid Award to fit the approved funds.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |